Grandbay East Header Image
Grandbay East Main Image
Current Projects


 

Current Projects - District E CIP/Safe Sidewalk Program/SNAP Items

CAPITAL IMPROVEMENT PROJECTS - COUNCIL DISTRICT E (KINGWOOD)

Project # Dept.  Project Name Address Zip Status

Completion Yr

F-000695 PARKS Lake Houston Park 25840 FM 1485  77357 Construction  2015
F-BGSC99 PARKS BG2020- Spring Creek Greenway Lands Spring Creek Greenway Lands Various Planning  2017
F-BGSP01 PARKS BG2020- US 59 P&R to Woodland Hills US Park and Ride to Woodland Hills   Planning  2019
G-000149 POLICE Marine Unit Dock Improvement 22619 W. Shorewood Loop  77336 Construction  2015
G-000153 POLICE Facility Paving Improvements Various Locations   Construction  2017
L-000095 SOLID WASTE Night Light & CCTV Security Provision  Various Locations  77037 Planning  2017


CURRENT PROJECTS

Project #
Dept
Project Name
Progress
End Date
N-320610-0113
PWE
Safe Sidewalk Program (Kingwood)
91%
2020
N-320610-0122
PWE
Safe Sidewalk Program (Package2)(Northpark)
80%
2020
R-00026509976-4
PWE
E.Coli Compliance Projects-Chlorination systems for Turkey Creek, Westway and 
37%
2020
S-000600-0043-4
PWE
Rehabilitation of Water Storage Tanks: District 51 GST-1, Rosewood EST-1, Braeswood GST-1, Sharpstown-2 GST-1, Eisenhower Park HPT-2 and
46%
2020

UPCOMING PROJECTS

Project #   Dept.  Project Name Design Start Design End 
R-000035-0006-3 PWE Force main Renewal and Replacement for Stroud, Bayfield, Bretshire, Woodland Ridge and Forest Shores Lift Stations May-2013 Jul-2017
R-000265-0102-3 PWE Metro Central, Upper Braes,White Oak and Kingwood West WWTP Improvements Mar-2013 Apr-2016
R-000801-0014-3 PWE Sewer Service to Unserved Areas Package 2 - Hidden Echo Sanitary Sewer Improvement and Plantation Hills Internal Sanitary Sewer Improvements Mar-2006 Jul-2015
R-000801-0015-3 PWE Sewer Service to Unserved Areas Package 3 - Magnolia Point Internal Sanitary Sewer Improvements Apr-2014 Mar-2017
S-000700-A014-3 PWE 12-inch Water Line Replacement along Walnut Street Jun-2015 Dec-2017
R-000265-0118-3 PWE Kingwood Central WWTP Improvements May-2015 Jun-2018
R-000267-0129-3 PWE Lift Station Renewal and Replacement - MacGregor #2, Epps, Kellogg, Scott #2, Glengyle and WCID #73 Apr-2015 May-2017


PROGRAMMED PROJECTS

Project # Dept.  Project Name Est. FY Est. Cost
N-100011-0001-3

PWE

Kingwood Drive Paving and Drainage: Loop 494 to West of HCFCD G103- 38-00  2020  $16,569,000


SAFE SIDEWALK PROGRAM - COUNCIL DISTRICT E (KINGWOOD)

Tracking #  Road  From  To  Project #
100605  Kingwood Drive  Greenbelt  Woodland Hills  N-0610A-0126-3
100708  Northpark Drive  Hidden Pines  Glade Valley  N-0610A-0126-3
100777  Lake Kingwood Trail  Kingwood Drive  Laurel Trail  N-0610A-0126-3
100900  Kingwood Drive  Lake Kingwood Trail  Valley Manor  N-0610A-0126-3
101302  West Lake Houston Pkwy  Breakwater Path  Edge Lake Blvd  N-0610A-0126-3

 

KINGWOOD SNC #43 2015 SNAP ITEMS

  • Install a gate in the fence between the Kingwood Park Community Center and the Metro Park and Ride and add a sidewalk from the fence to the community center parking lot.
  • Purchase a laptop computer, projector, and Microsoft Office software for use by the Kingwood Park Community Center and those people who use its facilities.
  • Install new rules sign at the Dylan Memorial Skate Park.
  • Move the paver blocks from the Heritage Center to the Kingwood Park Community Center park area.
 
 